Bally’s Corp. has not yet secured financing for an elevated plaza planned as part of its $1.19 billion mixed-use development surrounding the Athletics’ $2 billion Las Vegas ballpark, raising the prospect of a temporary structure when the stadium opens ahead of the 2028 season.
The disclosure came Thursday at a Las Vegas Stadium Authority meeting, where club and contractor officials reported that the 33,000-seat domed ballpark remains on schedule, according to the Associated Press. Buttress work is complete, the upper deck began rising in April, and a southeast-side parking garage will open with 1,500 spaces before expanding to 2,500 once construction wraps.

Tyler Van Eeckhaut, project director for contractors Mortenson-McCarthy, told the authority that the lower-suite level is progressing substantially, with rooms taking shape as a visible part of the stadium environment. That progress contrasts with the unresolved status of the plaza, which sits on the northwest side of the property and is intended to connect the ballpark with Bally’s resort development.
A’s vice chairman Sandy Dean said the club is developing contingency plans so a plaza will be ready by the 2028 opener, framing the situation as something the two sides need to work through together given Bally’s role in bringing the franchise to the site. Steve Hill, CEO and president of the Las Vegas Convention and Visitors Authority, pressed the A’s to bring a formal plaza plan to the next Stadium Authority meeting on Aug. 20, noting that any interim structure would eventually need to be removed to build the permanent retail and parking podium beneath it.
Plaza financing remains unresolved
The financing gap affects the elevated plaza within Bally’s planned mixed-use project, which is to include restaurants, shopping and entertainment alongside a hotel-casino and a 2,500-seat theater. The stadium is part of the overall development plan.

Ballpark Digest reported that the A’s have spent $400 million on the ballpark and that the project is on time and on budget. The outlet also reported that the potential plaza delay is the only delay identified in ballpark construction so far.
The stadium portion of the project continues to reach construction milestones while plans for the plaza are developed. Marc Badain, A’s president, said the first tranche of suites has sold out and 80% of season-ticket packages for seats behind home plate have been sold, with general public sales set to begin in coming months.
Source: ESPN/Associated Press